2015
- Environics prepared an EIA study (Form-B) for the addition of a new Skin Care Unit to produce the following:
- BB Cream.
- Jar Creams Garnier.
- Face Wash.
2016
- Environics prepared an EIA study (Form-B) for the second expansion in the plant to:
- Add an Oil Replacement production line.
- Establish a drying basin for the generated wastewater treatment sludge.
- Construct a pressure reduction room for the boiler’s Natural Gas.
Both studies encompassed: a description of the project and the relevant environmental laws and regulations. They assessed the environmental impacts, recommended appropriate mitigation measures for each impact, and developed the Environmental Management & Monitoring Plan.